SCC: Dominion Must Refile Its 2018 IRP

On Friday, December 7, the Virginia State Corporation Commission (“SCC” or “Commission”) entered an order directing Dominion Energy Virginia (“Dominion”) to revise and refile its 2018 Integrated Resource Plan (“IRP”). This order is significant in that the SCC has never rejected an IRP, or required a utility to refile its plan. We discuss several takeaways from this order below.

What is an IRP?

An IRP is a utility’s plan to meet customer demand and service obligations over a 15-year planning horizon. The IRP statute, Va. Code Section 56-599, directs utilities to evaluate various options to meet forecasted demand, including building new generation; entering into power purchase agreements with third parties; purchasing energy from the PJM market; and investing in energy efficiency resources. The statute directs the Commission to review the utility’s plan and to “make a determination … as to whether [the IRP] is reasonable and is in the public interest.” It is important to note that an IRP is not binding on the Commission or the utility in any way. The Commission states that approval of an IRP does not create any presumption that any particular resources are prudent.

Before determining whether Dominion’s 2018 plan is “reasonable,” however, the Commission wants more information. In particular, the SCC wants Dominion to update several aspects of the modeling used to generate the plan. Dominion was directed to provide these new modeling results within 90 days of the order.

“True Least Cost Plan”

First, the SCC wants Dominion to provide what it calls a “true least cost plan” that will “serve as a benchmark against which to measure the costs of all other alternative plans.” The Commission wants to know what Dominion’s modeling software would select if it were permitted to choose the least-cost resources to meet the company’s forecasted demand. The Commission’s order asserts that Dominion – instead of letting the model choose the lowest-cost resources mix – actually “forced” certain resources into the IRP. The Commission referenced Dominion’s offshore wind demonstration project as a resource that was “forced” into Dominion’s alternative plans.

“SB 966 Plan”

Second, the Commission wants Dominion to file a plan that incorporates all of what the SCC calls the Senate Bill 966 (“SB 966”) “mandates.” This legislation declared that it is “in the public interest” for Virginia utilities to construct or acquire up to 5,500 MW of new renewable energy resources. The legislation also referenced certain distribution and transmission undergrounding priorities. (Note that the Commission, in this and other orders, characterizes the priorities outlined by the General Assembly as “mandates.” The use of this term, however, is misleading when applied to renewable energy. SB 966, while declaring such renewable energy projects to be “in the public interest,” does not require utilities to make these investments, nor does it require the Commission to approve them.)

By requiring both a “Least Cost Plan” and a “SB 966 Plan,” the Commission wants to estimate the incremental costs of the SB 966 investments. The SCC may want to include this estimate in its final order on Dominion’s IRP. Moreover, the Commission may choose to include this analysis in one of the written reports provided Governor and the General Assembly regarding the implementation of Virginia’s electric regulation statutes.

Anticipated load growth

Next, the SCC directed Dominion to utilize the PJM load forecast for the Dominion Zone, which has a 15-year growth rate of 0.8%, versus Dominion’s 1.4%. At the evidentiary hearing, the Commission Staff and environmental advocates argued that Dominion’s internal load growth was too high, thus overstating the for need for new generation.

Solar capacity factors

The Commission also directed Dominion to update its modeling to use a 23% capacity factor for its solar facilities. A generation plant’s capacity factor represents the amount of time it is available and generating electricity. Dominion’s IRP assumes that new solar resources will achieve capacity factors of 26%, in part due to the use of single-axis tracking facilities which follow the sun, resulting in greater production. But the Commission noted that Dominion’s “existing [solar] resources have experienced actual capacity factors of approximately 20% on average over the last five years.” Therefore, the SCC split the difference between the actual, observed capacity factors and those forecasted by Dominion. The solar industry supported Dominion’s capacity factor projections, finding them to be achievable.

Pipeline and fuel costs

Finally, the Commission’s order does not address the proposed Atlantic Coast Pipeline (“ACP”), which would be constructed by affiliates of Dominion and may serve some of the company’s gas generation facilities. The SCC previously declined to review the ACP fuel supply contracts under the Virginia Affiliates Act, a statute which directs the Commission to approve any contracts entered into between public utilities and their affiliates.

The Commission did direct Dominion, in a footnote, to “include a reasonable estimate of fuel transportation costs … associated with natural gas generation facilities.” This could be an indication that the Commission does not believe Dominion’s forecasted gas costs are reasonable. Elsewhere in its order, however, the Commission seemed to express concern that “[Dominion’s] modeling was not permitted to select highly-efficient natural gas-fired combined-cycle facilities” and as a result Dominion’s modeling “forces in higher-cost resources [while] excluding other lower-cost resources [which] results in a more expensive plan.”

The SCC’s Order and other documents for this case are available online in Docket No. PUR-2018-00065. GreeneHurlocker represented the Solar Energy Industries Association in the evidentiary hearing at the SCC.

Should you have any questions about this case, please contact one of our energy regulatory attorneys.

SCC Approves New Large Customer Renewable Energy Tariff

wind turbines and solar arraysThe Virginia State Corporation Commission (“SCC” or “Commission”) just approved a new tariff that will give customers of Dominion Energy Virginia (“Dominion”) an additional option to purchase renewable energy. On November 6, 2018, the SCC entered a Final Order approving Dominion’s application to offer a voluntary tariff designated “Rate Schedule RG.” The tariff is available to large, non-residential customers who agree to purchase the output, including all environmental attributes, from particular renewable energy facilities.

Participating customers may request to purchase the output from specific types of generation resources, such as solar and wind energy facilities. Dominion would either construct a new renewable facility or enter into a contract with a third-party generator to obtain the renewable energy necessary to serve the customer. Schedule RG, therefore, presents an opportunity for customers to choose the type of renewable energy they want to purchase. For example, a customer could request that Dominion enter into a contract with a particular generator. Or the customer could request the utility to build a new renewable facility on the customer’s premises or in a particular geographic location. The minimum facility size is 1 MW in nameplate capacity.

Participation in Schedule RG is capped at 50 customers. The tariff is also designed to ensure that non-participating customers do not subsidize any of the costs associated with Schedule RG. For example, Dominion may not place any of the Schedule RG facility costs in its rate base or the cost of service charged to non-participating customers.

The financial transactions supporting Schedule RG are complex. Participating customers would stay on their existing tariff and continue to pay all existing utility riders. At the same time, however, customers would pay a fixed price to purchase the renewable energy and would receive a “Schedule RG Credit” that is based on the wholesale price of energy and the capacity of the facility. In this way, the Schedule RG arrangement is like a financial “swap.” That is, participating customers would agree to pay a pre-determined renewable energy contract price, but would also receive the market price for the energy, which would be sold by Dominion in the PJM wholesale market. Thus, Schedule RG is designed to approximate the actual market cost of renewable energy from particular generating facilities.

Several parties intervened in the case, including Walmart and two renewable and advanced energy trade associations. While several parties offered comments on the proposal, no party to the case opposed Schedule RG.

The SCC approved the application subject to several reporting requirements. The SCC also held that Schedule RG will expire after three years if no customers participate.

Finally, it is important to note that Schedule RG was not approved under Va. Code § 56-577 A 5 and would not constitute a 100% renewable energy tariff under this statutory provision. As we explained in our Regulatory Guide, this Code section authorizes any Virginia customer to purchase electricity “provided 100% from renewable energy” from non-utility suppliers, so long as the customer’s incumbent electric utility does not offer an SCC-approved tariff for 100% renewable energy. Therefore, if Dominion received approval to offer a 100% renewable energy tariff pursuant to Va. Code § 56-577 A 5, Dominion customers would lose their existing rights to shop for such energy.

Currently, no Virginia utility offers an SCC-approved 100% renewable energy tariff. Dominion and Appalachian Power have both applied for approval to offer such tariffs, which thus far have been rejected. In the last three years, the SCC has rejected two 100% renewable tariffs proposed by Appalachian Power and one proposed by Dominion. Dominion currently has one application pending, which would be available to residential and small commercial customers.

The SCC’s Final Order in Schedule RG, Case No. PUR-2017-00163, is available here. If you have any questions about Schedule RG or other renewable energy options offered by Virginia utilities, please contact one of our energy regulatory attorneys.

SCC Approves First Renewable Energy Projects

offshore wind projectOn Friday, November 2, the Virginia State Corporation Commission (“SCC” or “Commission”) approved the first major renewable energy investments by Dominion Energy Virginia (“Dominion”) following the passage of Senate Bill 966 (“SB 966”), the sweeping utility overhaul legislation enacted in March. SB 966 provides that it is “in the public interest” for Dominion and Appalachian Power Company to purchase or construct up to 5,000 MW of new wind and solar energy resources. The legislation specifically states that a wind demonstration project located off Virginia’s coast would be “in the public interest.”

The SCC approved a 12 MW, $300 million offshore wind demonstration project proposed by Dominion, which will be constructed 27 miles off the coast of Virginia Beach. While finding the project to be prudent, the SCC’s Final Order strongly suggests that the application would have been rejected absent legislation deeming such projects to be “in the public interest” as a matter of law.

The Commission’s Final Order stated that the wind proposal “would not be deemed prudent [under this Commission’s] long history of utility regulation or under any common application of the term.” The SCC noted that the offshore wind project, which will be constructed by a Danish energy developer, was not subject to competitive bidding and that the energy costs will be “26 times greater than purchasing energy from the market” and “13.8 times greater than the cost of new solar facilities.” Finally, the Commission found that the project is not needed for Dominion to ensure reliability or meet any forecasted demand. Nonetheless, the Commission concluded that, “as a matter of law,” the Commission’s “factual analysis” of the reasonableness of the project is “subordinate [to] the legislative intent and public policy clearly set forth [by the 2018 amendments.”

The Commission also approved Dominion’s request to purchase 80 MW of solar energy via a power purchase agreement (“PPA”) with a non-utility company, Cypress Creek Renewables. The Commission noted that, unlike the offshore wind project, Dominion customers would be protected from financial and performance risks of the project since the utility is purchasing the energy from private developers.

The Final Order in the offshore wind matter (Case No. PUR-2018-00121) is available here and the Final Order in the solar PPA matter (Case No. PUR-2018-00135) is available here. Please contact one of our energy regulatory attorneys if you have questions about either of these cases.

Dominion Files 2014 Integrated Resource Plan

Regulatory Alert:  At the end of last month, Dominion Virginia Power (Dominion) submitted its 2014 Integrated Resource Plan (the 2014 IRP), which covers the period 2015 through 2029, to the Virginia State Corporation Commission (SCC) for review.  Virginia law requires that these plans should, among other things, reflect a diversity of electric generation supply and cost-effective demand reduction contracts and services so as to reduce the risks associated with an over-reliance on any particular fuel or type of generation demand and supply resources and be consistent with Virginia’s energy policies set forth in Section 67-102.

The SCC will review the 2014 IRP and make a determination as to whether the 2014 IRP is reasonable and is in the public interest.  The SCC has not yet issued a procedural order in this case, and we will update this Alert as soon as that happens.  We are paying particular attention to this integrated resource plan proceeding in light of the Environmental Protection Agency’s June issuance of a Clean Power Plan, pursuant to draft rule 111(d), which would require a significant reduction in carbon emissions from existing sources of power generation.

GreeneHurlocker works with many clients operating in areas that may be impacted by the 2014 IRP proceeding. Please contact one of our energy lawyers if you have questions about the 2014 IRP, the EPA’s Clean Power Plan or any other issues relating to Virginia energy regulation.