Tel: 804.864.1100

Tel: 804.864.1100

Tag Archive: utility regulation

Calpine and Direct Energy Win Again, Continue to Provide Renewable Energy in Virginia

The Virginia State Corporation Commission (the “Commission”) denied Dominion Energy Virginia’s (“Dominion”) July 16, 2019 petitions for declaratory judgment in Case Numbers PUR-2019-00117 and PUR-2019-00118 by Final Order on September 18, 2019. Dominion’s petitions sought to have the Commission standardize “around the clock,” “control of renewable capacity” requirements for competitive service providers (“CSPs”) to serve customers under Virginia Code § 56-577 A 5 (“Section A 5”). That section provides a statutory right to customers of all classes to purchase “electric energy provided 100 percent from renewable energy” from a CSP unless the utility has its own 100% renewable energy tariff. Dominion’s application for a 100% renewable energy tariff is pending before the Commission, and Dominion had refused to process enrollments submitted by Calpine Energy Solutions, LLC (“Calpine”) and Direct Energy Business, LLC (“Direct Energy”) under Section A 5 in the interim and initiated these cases at the Commission.

The Commission previously granted Calpine’s and Direct Energy’s requests for injunctive relief, requiring Dominion to process enrollments while these cases are pending. We blogged about that here.

Dominion’s petitions took aim at Calpine and Direct Energy, seeking a determination that CSPs seeking to serve under Section A 5 must establish that they can supply customers with electric energy provided 100 percent from renewable energy on an “around the clock” basis and that the CSPs must have “control” over “renewable capacity.” The Commission flatly rejected Dominion’s positions and declared that both Calpine and Direct Energy provided information to reasonably establish that they have contracted for sufficient renewable energy to match renewable supply with a participating customer’s load on a monthly basis, which is consistent with Section A 5 and Commission precedent.

Regarding Commission precedent, the Commission refused to adopt Dominion’s interpretation of a prior order approving Appalachian Power Company’s Rider WWS (“Rider WWS Order”), which Dominion believes requires a CSP to have “control of sufficient renewable generation resources, including renewable capacity and associated renewable energy, to enable it to serve the full load requirements of the customers it intends to serve.” The Commission’s refused to provide the requested declaration, explaining that the Rider WWS Order did not require “’renewable capacity,’ nor did it define ‘full load requirements’ to mean (as argued by Dominion) ‘full load at all times’ or ‘full load requirements around the clock.’” Significantly, the Commission’s Final Order makes clear: “Nothing in [the Rider WWS Order], however, found that [Appalachian Power Company’s] proposal was the only way to comply with Section A 5.”

The crux of the Commission’s decision relied upon its close reading of Section A 5. “The plain language of Section A 5 also says ‘energy,’ not ‘capacity.’” In acknowledging this critical distinction, the Commission put a finer point on Dominion’s efforts to muddy the waters between “energy” and “capacity” requirements, despite the fact that Section A 5 requires customers to purchase renewable electric “energy” – not “capacity.” In the same way, the Commission examined closely Dominion’s request for more stringent matching standards, noting several times that in other proceedings, Dominion has taken positions inconsistent with those it takes in its petitions for declaratory judgment: “There is nothing in the plain language of Section A 5, however, that mandates Dominion’s “100% of the time” (i.e., “around the clock”) requirement.”

The Commission also scrutinized Dominion’s proposal from a consumer protection perspective, finding that Dominion’s “100% of the time” standard would adversely affect a customer’s right to purchase renewable energy – essentially, upending the entire aim of Section A 5. Dominion’s argument would read certain renewable generating sources (e.g., wind or solar) out of the statute because of their intermittency regardless of the amount of nameplate capacity or peak load served. Finally, the Commission evaluated Dominion’s proposed standard with special focus on the fact that Virginia’s existing monthly matching standard is already one of the most stringent in the country for states with renewable energy markets, as other states generally require customer load and renewable supply to be matched on a yearly basis.

The Commission declined to accept Dominion’s proposed language that would adopt a new standard for Section A 5, presented for the first time at the hearing on August 20, 2019. The Commission reasoned that to do so would contravene the Commission’s past rejection of “capacity,” “peak demand,” or “100% of the time” requirements – including the Commission’s rejection of Dominion’s past requests (notably in the Rider WWS proceeding) for “around the clock” supply of renewable energy pursuant to Section A 5. Similarly, the Commission held that Dominion’s proposal at the hearing regarding what Dominion believes the current law should reflect “improperly goes beyond the specific relief requested in the Petitions for Declaratory Judgment… [and] does not reflect current Commission precedent and is otherwise procedurally improper.”

The Conclusion in the Commission’s Final Order makes clear that:

  • Commission precedent permits a CSP to match customer load with renewable supply on a monthly basis and does not requires CSPs to provide “renewable capacity”;
  • Direct Energy and Calpine have satisfactorily demonstrated that they can supply their customers with electric energy provided 100 percent from renewable energy on a monthly matching basis;
  • Direct Energy and Calpine are required to continue providing information as directed in the Final Order – regarding each CSP’s customer load and wholesale generation contracts, in accordance with Section A 5, the Commission’s Rules Governing Retail Access to Competitive Energy Services, as well as Dominion’s Competitive Service Provider Coordination Tariff; and
  • Even if Dominion’s new proposal were procedurally appropriate, which it is not, the Commission further finds that: (1) the plain language of Section A 5 does not mandate – as a matter of law – adoption of Dominion’s proffered standard; and (2) matching customer load with renewable supply on a monthly basis represents a reasonable standard under Section A 5, and Dominion’s proposed standard is not necessary in order to implement Section A 5 in a reasonable manner,

GreeneHurlocker represents Calpine in these proceedings.
If you have questions about this case or electric service in general, please contact one of GreeneHurlocker’s energy and regulatory lawyers.

Maryland PSC Requests Comments on New RFP for Retail Suppliers

The Maryland Public Service Commission issued a Notice of Opportunity to Comment seeking comments on a new “Retail Supplier Load Shaping RFP.” The Commission want to consider “programs designed to demonstrate the ability to shape residential load profiles using innovative business models.” Comments on the RFP, a copy of which is attached to the Notice, are due April 9, 2019.

The RFP states that:

“The primary goal of this RFP is to identify pilots that demonstrate an ability to shape customer load profiles through load shifting, peak shaving, and energy efficiency. Applicants can propose any mechanism for load shaping such as sending appropriate price signals (real time rates), using technology to control usage (controllable thermostats), payment of rebates or behavioral modification treatments. A secondary goal is to test whether load shaping can lower customer bills or reduce the customers’ overall effective rate for electricity by avoiding energy usage during high cost periods. Customer satisfaction will be surveyed at the pilot’s conclusion.”

There’s some background here. In early 2017, the Commission established Public Conference 44 with various working groups. Three working groups involved areas where the retail supply market could be improved or could expand to provide additional services to Maryland customers. One of those working groups involved rate design issues and sought to develop TOU pilot programs. The Commission approved TOU programs for the utilities, which are now being marketed to customers. The Commission also approved an RFP to establish retail supplier programs. However, and the Commission in November 2018 issued a letter order holding that the bids received were not compliant and directed the utilities to reject them.

The Commission has now proposed changes to the prior RFP and has issued the current Notice to elicit more involvement from retail suppliers in a rate design program. The Commission seems determined to engage the retail supplier community in this effort, stating that, “[a]s Maryland moves forward with grid modernization, the retail supply community can play an important role in supporting policy goals, including more active efforts to shape load profiles.”

If you have questions or would like more information about community solar projects or other regulatory issues, contact Brian Greene or any of our mid-Atlantic energy lawyers.

Maryland Solar Groups Seek Community Solar Utility Consolidated Billing

On March 20th, the Climate Access Fund and Solar United Neighbors of Maryland filed a petition asking the Maryland Public Service Commission to require Maryland utilities to provide consolidated billing for subscriber organizations participating in Maryland’s Community Solar Pilot Program. The petitioners want utilities to include community solar subscription charges on customer bills. Today, subscriber organizations have to separately bill community solar subscribers. The stated objective of the petition is to make consolidated billing available for low and moderate income customers, helping to improve the economics of participating in the program. Two alternatives are proposed in the petition: (1) consolidated billing for all subscriber organizations or (2) consolidated billing for low and moderate income-focused community solar projects only.

We will be on the lookout for a response from the Commission and opportunities to comment on the community solar consolidated billing proposal. If you would like to review the filing, a copy of the petition is available on the Maryland Public Service Commission’s website: Mail Log # 224384.

For more information about Maryland’s Community Solar Pilot Program, check out our previous blog posts:

Maryland Proposes Community Solar Pilot Program Regulations
Community Solar Growing in Mid-Atlantic
Continued Progress for Community Solar in Maryland

If you have questions or would like more information about community solar projects or other regulatory issues, contact Eric Wallace or any of our mid-Atlantic energy lawyers.

SCC Approves New Large Customer Renewable Energy Tariff

wind turbines and solar arraysThe Virginia State Corporation Commission (“SCC” or “Commission”) just approved a new tariff that will give customers of Dominion Energy Virginia (“Dominion”) an additional option to purchase renewable energy. On November 6, 2018, the SCC entered a Final Order approving Dominion’s application to offer a voluntary tariff designated “Rate Schedule RG.” The tariff is available to large, non-residential customers who agree to purchase the output, including all environmental attributes, from particular renewable energy facilities.

Participating customers may request to purchase the output from specific types of generation resources, such as solar and wind energy facilities. Dominion would either construct a new renewable facility or enter into a contract with a third-party generator to obtain the renewable energy necessary to serve the customer. Schedule RG, therefore, presents an opportunity for customers to choose the type of renewable energy they want to purchase. For example, a customer could request that Dominion enter into a contract with a particular generator. Or the customer could request the utility to build a new renewable facility on the customer’s premises or in a particular geographic location. The minimum facility size is 1 MW in nameplate capacity.

Participation in Schedule RG is capped at 50 customers. The tariff is also designed to ensure that non-participating customers do not subsidize any of the costs associated with Schedule RG. For example, Dominion may not place any of the Schedule RG facility costs in its rate base or the cost of service charged to non-participating customers.

The financial transactions supporting Schedule RG are complex. Participating customers would stay on their existing tariff and continue to pay all existing utility riders. At the same time, however, customers would pay a fixed price to purchase the renewable energy and would receive a “Schedule RG Credit” that is based on the wholesale price of energy and the capacity of the facility. In this way, the Schedule RG arrangement is like a financial “swap.” That is, participating customers would agree to pay a pre-determined renewable energy contract price, but would also receive the market price for the energy, which would be sold by Dominion in the PJM wholesale market. Thus, Schedule RG is designed to approximate the actual market cost of renewable energy from particular generating facilities.

Several parties intervened in the case, including Walmart and two renewable and advanced energy trade associations. While several parties offered comments on the proposal, no party to the case opposed Schedule RG.

The SCC approved the application subject to several reporting requirements. The SCC also held that Schedule RG will expire after three years if no customers participate.

Finally, it is important to note that Schedule RG was not approved under Va. Code § 56-577 A 5 and would not constitute a 100% renewable energy tariff under this statutory provision. As we explained in our Regulatory Guide, this Code section authorizes any Virginia customer to purchase electricity “provided 100% from renewable energy” from non-utility suppliers, so long as the customer’s incumbent electric utility does not offer an SCC-approved tariff for 100% renewable energy. Therefore, if Dominion received approval to offer a 100% renewable energy tariff pursuant to Va. Code § 56-577 A 5, Dominion customers would lose their existing rights to shop for such energy.

Currently, no Virginia utility offers an SCC-approved 100% renewable energy tariff. Dominion and Appalachian Power have both applied for approval to offer such tariffs, which thus far have been rejected. In the last three years, the SCC has rejected two 100% renewable tariffs proposed by Appalachian Power and one proposed by Dominion. Dominion currently has one application pending, which would be available to residential and small commercial customers.

The SCC’s Final Order in Schedule RG, Case No. PUR-2017-00163, is available here. If you have any questions about Schedule RG or other renewable energy options offered by Virginia utilities, please contact one of our energy regulatory attorneys.

SCC Decision Expands Access to Competitive Electric Supply

transmission towers for electricityWhile many political observers were focused on Senate Bill 966, the omnibus utility legislation that was just passed by the General Assembly, the Virginia State Corporation Commission (“Commission” or “SCC”) recently issued an important decision affecting customers’ rights to purchase energy from competitive suppliers.

On February 21, 2018, in Case No. PUR-2017-00109, the Commission approved the first ever “customer aggregation” petition under § 56-577 A 4 of the Code of Virginia. As explained in detail below, this section of the Code allows customers to aggregate their demand for the purposes of satisfying the 5 MW demand threshold required to purchase generation from non-utility companies.

In most circumstances, Virginia’s incumbent electric utilities, including Dominion Energy Virginia (“Dominion”), have a monopoly on the sale of electricity in their service territories. Customers must purchase energy from their utility. Virginia law, however, provides two exceptions to the utilities’ monopoly rights. (Under these two exceptions, customers may purchase generation from non-utility suppliers. But shopping customers must still pay for the utility’s distribution services.)

First, under Va. Code § 56-577 A 5, customers may purchase “100 percent renewable energy” from competitive suppliers if  the customer’s monopoly electric utility does not offer an SCC-approved 100% renewable energy tariff. No utility currently offers an SCC-approved 100% renewable tariff.

Second, Va. Code § 56-577 A 3 law allows large customers with annual demands over 5 MW to purchase generation from competitive suppliers. Importantly, the law also allows a group of customers to “aggregate” their demands in order to reach the 5 MW threshold. The statute treats large customers with multiple meter locations as different customers but allows them to aggregate to meet the 5 MW threshold. Once aggregated, the group will be treated as a “single, individual customer” under the law. Before allowing an aggregation, however, the Commission must find that the requested aggregation would be “consistent with the public interest.”

SCC Case No. PUR-2017-00109 was the first test of this statutory provision – that is, the first time a group of customers sought to combine their demands in order to reach the 5 MW threshold. In this case, Reynolds Group Holdings, Inc. (“Reynolds”), a metals and packaging manufacturer, petitioned the SCC for approval to aggregate six of its retail accounts in Dominion’s service territory.

Dominion and Appalachian Power Company (“APCo”) intervened in the case and opposed the petition. Dominion argued that allowing customers to aggregate their demand “would unreasonably expand the scope of retail access [and would] have the potential effect of eroding a significant portion of the utility’s jurisdictional customer base.” Dominion also suggested that the General Assembly – despite authorizing customer shopping and aggregation – intended to allow retail choice “only in limited circumstances.”

But the SCC, relying on the plain language of Va. Code § 56-577 A 4, rejected Dominion’s and APCo’s arguments and approved the petition. Dominion and APCo have until March 23, 2018, to appeal the decision to the Virginia Supreme Court.

The SCC is also currently considering additional aggregation requests filed by over 160 Walmart customer accounts in Case Nos. PUR-2017-00173 and PUR-2017-00174. (In both of these cases, GreeneHurlocker is representing competitive suppliers who are supporting approval of Walmart’s aggregation requests.)

Should you have any questions about customer aggregation or competitive supply options in Virginia, please contact one our regulatory attorneys.

Additionally, GreeneHurlocker recently published Principles of Electric Utility Regulation in Virginia, which provides a plain-English explanation of Virginia’s electric utility laws, including the statutes affecting retail choice.

Delaware Sets Hearing for Retail Market Enhancements

The Delaware Public Service Commission has established a March 8, 2018 hearing date to consider retail choice enhancements.

The Delaware General Assembly meets in the Leg...

The Delaware General Assembly meets in the Legislative Hall in Dover. (Photo credit: Wikipedia)

The enhancements include a purchase of receivables program; “seamless moves” where customers may move within the utility service territory and maintain their supplier; “ instant connects” where customers may sign up with a supplier on their first day of service; an “enroll with your wallet” program where customers may enroll with a supplier without the use of their utility account number or other utility-assigned identifier; improvements to the Commission’s shopping website; and utility bill inserts to promote choice.

The proceeding has been pending since the end of 2015 when the Electricity Affordability Committee created by the Delaware General Assembly filed a petition with the Commission. Since that time, the parties have filed written comments and participated in working group meetings. Also, the case was stayed for a period of time while the parties and the Commission finalized amendments to the Delaware Electric Supplier Rules.

The case will be heard before a hearing examiner. The primary participants in the case are the Staff of the Commission, Delmarva Power, the Delaware Public Advocate, and the Retail Energy Supply Association (RESA). GreeneHurlocker is representing RESA in the proceeding.

For more information, please contact one of our regulatory attorneys.

Dominion Buying Gas Distributor Questar

Dominion Resources Inc. (“Dominion”) announced Monday, February 1, 2016, that it plans to purchase Utah-based Questar Corporation (“Questar”), a natural gas distributor, for approximately $4.4 billion in an all-cash deal.  Purchasing Questar will expand Dominion’s customer base to customers in Western states.  With Questar’s acquisition, Dominion would serve approximately 2.5 million electric customers and 2.3 million gas customers in seven states.  In addition, Dominion would operate more than 15,000 miles of natural gas transmission, gathering and storage pipelines.

The acquisition is set to close by the end of 2016, pending approval from Questar’s shareholders, the Federal Trade Commission, and, if needed, the Utah Public Service Commission and the Wyoming Public Service Commission.  The companies indicated they will also give information about the transaction to the Idaho Public Utilities Commission. After closing, Questar will remain headquartered in Salt Lake City, Utah, operating as a unit of Dominion.

If you have questions about the Dominion acquisition or utilities regulation in Virginia or the mid-Atlantic, please contact one of our energy lawyers.